Intumescent Coating Application and Certification, Westfield Energy Recovery Facility
Location: Westfield Energy Recovery Facility, Lochgelly, Fife, ScotlandScope of Work: Application and certification of intumescent fire protection coating system to structural steelwork across 42 locations within the plant.Team Deployment: IRATA-qualified rope access technicians and IPAF-certified MEWP operators, working under a nominated rope access supervisor.Access Method: Primary access via boom-lift MEWPs fitted with anti-entrapment devices; IRATA…
Air-Cooled Condenser (ACC) Duct Touch-Up Painting
Location: Skelton Grange Energy-from-Waste FacilityScope of Work: Touch-up painting of ACC steam ducts, turbine ducting, diagonal supports, undersides and ACC fans outside the boiler hall.Team Deployment: IRATA-qualified rope access technicians supervised by iCATS-trained supervisor. Access Method: MEWP (cherry picker) and rope access, with IRATA-qualified technicians. Overview: Think Access was engaged to carry out the full…
Over-Water Concrete Repair & Protective Coating Works
Location: Brentford Docks Marina, West LondonScope of Work: Visual inspection, preparation and concrete repair of a failed over-water repair section; application of protective coating system to match existing finish.Team Deployment: 3 IRATA-qualified rope access technicians. Access Method: IRATA-compliant rope access, weight trolley anchor system rigged and rescue provisions set specific to the over-water work zone….
ACC Overhang Cladding Installation & A-Frame Remedial Works
Location: West BromwichScope of Work: Inspection and remedial trimming of internal A-frame cladding panels; installation of approx. 60 corrugated cladding sheets to the ACC overhang structure via IRATA rope access.Team Deployment: 3 IRATA-qualified rope access technicians. Access Method: IIRATA-compliant rope access — ropes rigged and tension lines set specific to each working area across the…
Rope Access Steel Painting — Industrial Waste Bunker
Location: Industrial waste bunker facility, Riverside 2Scope of Work: Full steelwork restoration including surface cleaning, hole repair and sealing with Belzona, grating removal, and repainting of all steel surfaces from handrail level down to concrete.Team Deployment: 3 IRATA-qualified rope access technicians Access Method: IRATA‑compliant rope access, purpose-rigged rope systems installed specific to the structure Overview:…
Long‑Term Rope Access Maintenance & Operational Support
Location: Skelton GrangeScope of Work: Full‑time rope access technicians providing ongoing maintenance, inspections, and operational supportTeam Deployment: IRATA‑certified rope access technicians stationed permanently on site Access Method: IRATA‑compliant rope access, rigging, and industrial maintenance techniques Overview: Think Access Ltd. have been engaged to provide full‑time rope access technicians at Skelton Grange, ensuring the site remains…